LHWP 2024 Tunnel Shutdown

Company

Raubex Construction

Location

Delivery Tunnel North (DTN) and Ash River, Lesotho Highlands Water Project (LHWP)

Client

Trans Caledon Tunnel Authority (TCTA)

The LHWP 2024 Shutdown project was awarded on 9 September 2024 for completion on 31 March 2025, valued at R357.82 million over a six-month contract period. The works involved inspection and repairs of the Delivery Tunnel North (DTN) and erosion protection to the Ash River. Key activities included pre-shutdown preparations such as load testing, pump installation, and valve repairs; grit blasting and relining of steel sections; inspection and repair of concrete-lined sections; refurbishment and reinstallation of valves in the dewatering shaft; gabion repairs and gunniting; inspection and repair of the Ash Outfall; installation of stop logs; and shaping and placing rip rap along Ash River banks. Additional work included gabion repairs at the Caledon Dewatering Shaft and new fencing installation at Little Caledon.